This SWCD project for watershed protection and flood prevention in Maui County, Hawaii, was implemented under the authority of the Watershed Protection and Flood Prevention Act (P.L. 566, 83rd Congress, 68 Stat. 666), as amended. The Honolua Watershed Project encompasses eight desilting basins, about 0.8 miles of floodwater diversions, about 0.7 miles of floodwater channels, land treatment measures on about 24,000 acres, four bridges, relocation of three water mains, and controlled use of flood plain areas.

Sponsoring Agencies: West Maui Soil & Water Conservation Districts and the County of Maui.

KAHANA DAMProject Agreement: February 8, 1983Cost: $1,501,186Construction Period: June 14, 1983 – June 18, 1984

KAHANA DAM
Project Agreement: February 8, 1983
Cost: $1,501,186
Construction Period: June 14, 1983 – June 18, 1984

NAPILI 4-5Project Agreement: June 26, 1984Cost: $257,396Construction Period: September 21, 1984 – February 27, 1985

NAPILI 4-5
Project Agreement: June 26, 1984
Cost: $257,396
Construction Period: September 21, 1984 – February 27, 1985

 
NAPILI 2-3Project Agreement: July 3, 1985Cost: $2,161,291Construction Period: January 31, 1986 – February 24, 1988Contractor: DNL Construction Inc.

NAPILI 2-3
Project Agreement: July 3, 1985
Cost: $2,161,291
Construction Period: January 31, 1986 – February 24, 1988
Contractor: DNL Construction Inc.

 
MAHINAHINA CHANNELProject Agreement: September 27, 1990Cost: $2,372,876Construction Period: March 19, 1991 – March 8, 1992Contractor: Abhe & Svoboda Inc.

MAHINAHINA CHANNEL
Project Agreement: September 27, 1990
Cost: $2,372,876
Construction Period: March 19, 1991 – March 8, 1992
Contractor: Abhe & Svoboda Inc.

 
Napili Damage RepairProject Agreement: August 28, 1989Cost: $207,254Construction Period:November 23, 1989 – March 27, 1990Contractor: DNL Construction Inc.

Napili Damage Repair
Project Agreement: August 28, 1989
Cost: $207,254
Construction Period:
November 23, 1989 – March 27, 1990
Contractor: DNL Construction Inc.

KAHANA DAM INLET REPAIRProject Agreement: August 28, 1995Cost: $12,020Construction Period:October 23, 1995 – October 28, 1995Contractor: Geltech Constructors Inc.

KAHANA DAM INLET REPAIR
Project Agreement: August 28, 1995
Cost: $12,020
Construction Period:
October 23, 1995 – October 28, 1995
Contractor: Geltech Constructors Inc.

 
HONOKOWAI DAM—MAHINAHINA BASINProject Agreement: June 10, 1983Cost: $3,504,747Construction Period: September 6, 1994 – Novem

HONOKOWAI DAM—MAHINAHINA BASIN
Project Agreement: June 10, 1983
Cost: $3,504,747
Construction Period: September 6, 1994 – Novem